Energization of Vulcanesti–Chisinau power line might take place in next June

The installation works within the project on construction of the Vulcanesti–Chisinau power line are to be completed by the end of May, and the energization of the line is planned for next June. State Secretary of the Energy Ministry Carolina Novac has made statements to this effect.

The official said that the implementation level had reached 75 per cent at the 400 kV Vulcanesti Substation, at the Chișinău Substation – 80 per cent, while on the power line construction side the progress is 95 per cent.

"In terms of schedule, the installation works are meant to be completed by the end of May. The contract is valid until the end of June, and the energization of the line is planned for June 2026. We have weekly monitoring and verification meetings, so that we can ensure the work is carried out according to the indicated timeline," said Carolina Novac.

The Vulcanesti–Chisinau power line has a length of approximately 157 km and connects the 400 kV Vulcanesti Substation with the 330 kV Chisinau Substation. The transmission capacity of the line is up to 630 MVA, which will allow coverage of more than 50 per cent of Moldova’s consumption during peak periods. The Vulcanesti–Chisinau overhead power line is part of the Moldova Power System Development Project, financed by the World Bank Group. The total value of the project is approximately 61 million euros, of which around 27 million euros is allocated for the construction of the power line.

The project is implemented by Moldova’s government, through the Energy Ministry and UCIPE – the Energy Projects Implementation Unit, and the direct beneficiary is the state-owned enterprise Moldelectrica.

 


 
Latest News
/ 7 days ago

Railway of Moldova enterprise separates infrastructure of freight transport from passenger one; deputy PM announces when reform to be completed

/ 7 days ago

Report presented in Moldova's parliament: state-owned joint stock companies, enterprises generate profit of about 3.1 billion lei in 2025

/ 7 days ago

Energy infrastructure investments to be financed through corporate bonds: Memorandum signed in Chisinau

/ 16 November, 2026

Public-sector salaries to increase by 15.7 per cent on average in Moldova as of January 1, 2027: draft voted on by parliament

/ 16 November, 2026

Reform of public-sector pay system examined by Parliament: higher salaries for about 172,000 employees

/ 16 November, 2026

Citizens can invest in government securities: new subscription round launched

/ 14 November, 2026

PHOTO // Agricultural market from Ungheni city of Moldova modernized with over 18 million lei

/ 13 November, 2026

PHOTOS // Railway of Moldova enterprise tests new rail route between Straseni, Chisinau and Sangera

/ 13 November, 2026

Moldovan Ambassador, Chinese officials discuss country’s inclusion in China’s tourist destinations program

/ 13 November, 2026

PHOTO // National Bank of Moldova launches commemorative coin dedicated to Nadia Comăneci and first perfect 10 in gymnastics history

/ 12 November, 2026

Moldovan economic development minister, U.S. Ambassador to Moldova discuss opportunities to deepen bilateral economic relations

/ 12 November, 2026

National Bank of Moldova: annual average inflation rate trended upward in third quarter of 2026, driven by external factors

/ 12 November, 2026

Electricity from European and Romanian markets reaching Chisinau Electricity Center via Vulcănești–Chisinau Power Line for more than 48 hours

/ 12 November, 2026

Diesel price falls below 35-lei threshold in Moldova