From Ungheni to Iasi on European-Gauge railway: Moldovan deputy PM provides details on project, construction timeline

Tenders for the construction of the first electrified railway with European gauge, which will connect Moldova with Romania, have been launched on both banks of the Prut River. The first section will link the city of Ungheni with Iasi, and trains are expected to travel at speeds of up to 140–160 km/h. The announcement was made by Deputy Prime Minister, Infrastructure and Regional Development Minister Vladimir Bolea during the “La 360 de grade” (At 360 Degrees) programme.

According to the official, the project benefits from financial support from the European Union and involves the construction of a new railway line that will be electrified and compatible with European standards. The minister emphasized that Moldova currently has no electrified railway lines.

“The tender for the construction of the first section has been launched. The money comes from the European Union, and the cities of Ungheni and Iasi will be interconnected by a new railway line with European gauge and, most importantly, electrification. Of all types of transport, the cheapest is water transport, followed by rail, and, within rail transport, electrified railways are the most efficient type of traction. Moldova currently has no electrified railway lines. With the support of the European Union, we will build the first railway section of this kind, and both the Romanian and Moldovan sides have launched their tenders,” Vladimir Bolea said.

The next stage involves extending the European railway infrastructure from Ungheni to Chisinau. For this section, the authorities have secured European funding to prepare a feasibility study, which is expected to be completed in the first months of 2028. The new line will be built in parallel with the existing one, without replacing it, and will reach the area of the Chisinau International Airport.

“In Chisinau, this project will end outside the airport. We need to build a European railway, in parallel with the existing one, not instead of it, in accordance with all the new construction rules and standards. This document is expected to be completed in the first months of 2028, on the basis of which we will determine how much this route will cost. Subsequently, together with the financial resources provided by the European Union, we will move on to the construction process,” the minister said.

Asked whether the project could be completed by 2030, the year in which Moldova aims to join the European Union, Vladimir Bolea said that he would like this to happen, but that the deadline depends on more factors.

“I very much want this to happen. It depends on many factors, but, as you can see, it is very important to me that Moldova does not fall behind regions, such as Iasi, Botoșani and Suceava in the north, or Galati in the south. We need to develop evenly,” the official said.

The minister emphasized that the development of transport infrastructure was essential for attracting investment and increasing economic competitiveness. In his opinion, the lack of fast transport connections may put Moldova at a disadvantage compared with regions of Romania.

“There are many investors who do not come to a country where there is no motorway. Even if there are good roads passing through towns, it is much more complicated to travel at 40, 50 or 60 percent of the expected speed when you have bought a truck worth 100,000 euros. It has an economic operating cycle: it must reach its destination within a few hours and unload its cargo. We are talking about extremely important logistics factors, so that the owner can recover the investment and pay the bills for that truck. (...) Logistics is extremely important and is a major component in determining the export price from Moldova,” Vladimir Bolea added.

The railway connection project between Ungheni and Iasi is part of Moldova’s efforts to integrate into the European transport network. The use of European gauge would enable a more efficient connection with Romania’s railway infrastructure, reducing the need for wheelset changes or transshipment operations at the border.


 
Latest News
/ 7 days ago

EU prepares new financial package for Moldova; European Commissioner for Enlargement says package to be available as of 2028

/ 7 days ago

Moldovan PM says money of 30-million-euros-worth support, announced by EU, to go directly to people for payment of invoices in next winter

/ 7 days ago

EU to provide Moldova with 30 million euros in support to reduce energy vulnerability, assist citizens during cold season

/ 7 days ago

Energy system of the Republic of Moldova operated stably over past week, with no major incidents - Energy Ministry says

/ 7 days ago

Republic of Moldova to receive loan of about 976 million lei from Japan to invest in agricultural modernization

/ 7 days ago

Measures to streamline border traffic: two additional control lanes put into operation at Giurgiulești–Galați crossing

/ 7 days ago

Five wine producers from Moldova awarded at Asia Wine Trophy 2026

/ 06 November, 2026

PHOTO // Republic of Moldova represented for first time with national pavilion at China International Import Expo

/ 06 November, 2026

Gasoline, diesel to become cheaper over weekend

/ 06 November, 2026

Moldovan spirits win 12 medals at international competition in Brussels

/ 05 November, 2026

Moldovan government announces completion of 88 km of national roads in first 100 days in office

/ 05 November, 2026

Moldova negotiates access of animal origin products to market of Qatar

/ 05 November, 2026

BNM raises base rate applied to main short-term monetary policy operations

/ 05 November, 2026

PHOTO // Hâncești–Lăpușna–M1 road rehabilitated along 37 kilometers