Vulcănești–Chișinău power line could become operational next week

Vulcănești–Chișinău power line could be put into operation next week if the technical tests proceed without problems. Energy Minister Dorin Junghietu made the statement during 360 Degrees program, where he provided details about the final steps required to operationalize the project.

According to the minister, the commission responsible for accepting the construction and installation works was convened last week, while another meeting is scheduled for this week to assess whether the works have been completed.

“Last week, the commission responsible for accepting the construction and installation works was convened. This week, the commission is due to meet once again to confirm the completion of the construction works and allow the line to be energized, followed by 24–48 hours of testing to ensure that the entire project operates under voltage, and after that, testing under load,” said Dorin Junghietu.

The Energy Minister noted that, according to information provided by the contractor, efforts are planned through the end of this week to energize the line and conduct the first technical tests.

“According to what the contractor communicated today, the plan is to make maximum efforts by the end of the week to energize the line for the comprehensive testing of the entire project and, after the first test is completed, to proceed with the load test. If everything goes well and there are no surprises, so to speak, the line should be operational next week,” the official explained.

Dorin Junghietu said that if all checks are successfully completed and no unforeseen problems arise, the power line could become operational as early as next week.

The Vulcănești–Chișinău overhead power line, approximately 157 kilometers long and operating at 400 kV, is a strategic project for the energy security of the Republic of Moldova. The new infrastructure will enable electricity to be transmitted from Romania and the European market directly to the center of the country, reducing dependence on networks crossing the Transnistrian region.

The line will be able to transmit more than 50% of the country’s electricity consumption during peak periods. Construction of the line and work at the Vulcănești Substation have been completed, while acceptance procedures and technical checks are underway at the Chișinău Substation, which are necessary to commission the entire system.


 
Latest News
/ 7 days ago

Railway of Moldova enterprise separates infrastructure of freight transport from passenger one; deputy PM announces when reform to be completed

/ 7 days ago

Report presented in Moldova's parliament: state-owned joint stock companies, enterprises generate profit of about 3.1 billion lei in 2025

/ 16 November, 2026

Energy infrastructure investments to be financed through corporate bonds: Memorandum signed in Chisinau

/ 16 November, 2026

Public-sector salaries to increase by 15.7 per cent on average in Moldova as of January 1, 2027: draft voted on by parliament

/ 16 November, 2026

Reform of public-sector pay system examined by Parliament: higher salaries for about 172,000 employees

/ 16 November, 2026

Citizens can invest in government securities: new subscription round launched

/ 14 November, 2026

PHOTO // Agricultural market from Ungheni city of Moldova modernized with over 18 million lei

/ 13 November, 2026

PHOTOS // Railway of Moldova enterprise tests new rail route between Straseni, Chisinau and Sangera

/ 13 November, 2026

Moldovan Ambassador, Chinese officials discuss country’s inclusion in China’s tourist destinations program

/ 13 November, 2026

PHOTO // National Bank of Moldova launches commemorative coin dedicated to Nadia Comăneci and first perfect 10 in gymnastics history

/ 12 November, 2026

Moldovan economic development minister, U.S. Ambassador to Moldova discuss opportunities to deepen bilateral economic relations

/ 12 November, 2026

National Bank of Moldova: annual average inflation rate trended upward in third quarter of 2026, driven by external factors

/ 12 November, 2026

Electricity from European and Romanian markets reaching Chisinau Electricity Center via Vulcănești–Chisinau Power Line for more than 48 hours

/ 12 November, 2026

Diesel price falls below 35-lei threshold in Moldova